HORTICULTURE RESEARCH & ANALYSIS

One hectare.
Two locations.
All cost lines.

Tomato production costs and energy-related CO₂ emissions: Netherlands versus Agadir.

A transparent, line-by-line comparison covering labour, energy, water, growing supplies, packaging, capital, financing and operating overhead. Both locations are modelled as one-hectare unlit tomato greenhouses; local energy supply differs.

Einstein calculating energy, costs and greenhouse emissions for Westland Agadir Centre
ENERGY · LABOUR · PRODUCTIONOpen figures and traceable assumptions
01 / RESULT

Annual production cost, including capital charges

Scenario results per hectare at an assumed saleable output of 400 tonnes per year at each site. These figures are not verified farm accounts.

Netherlands / tonne€2.301,57€920.628,44 / hectare / year
Agadir / tonne€1.118,87€447.548,14 / hectare / year
Modelled difference€1.182,7051,4% lower in the Agadir scenario — not a measured saving
Scope and limits: Figures are copied from the 15 November 2026 cost model. Many labour, energy, land, equipment and yield inputs are assumptions. The cost totals extend to the regional export hub, not to the final European buyer. International shipping and customs are still unpriced.
02 / COMPARISON BASIS

Same growing area and equipment standard. Different local energy provision.

Identical growing structures do not guarantee identical crop yields. The equal yield assumption is used only to compare the individual cost components.

InputNetherlandsAgadirStatus
Net greenhouse growing area10.000 m²10.000 m²Common project size
Saleable tomato yield400 t/year400 t/yearAssumption, not field-verified
Artificial grow lightingNoneNoneProject design
Greenhouse structure and crop automationSame basisSame basisSupplier quote needed
Photovoltaic panelsNo installation in reference case3 kWp scenarioSite-specific energy design
Solar thermal storageNot included in Dutch modelIncluded in Agadir investment budgetEngineering and supplier quote needed
Fossil heatingGas-heated reference caseNo fossil heatingDifferent climate provisions
Water recyclingYesYesWater sourcing and costs open
Grower and harvest work7.500 hours/year7.500 hours/yearAssumed same hours; actual staffing not confirmed

An important distinction: the Dutch 209.000 m³ figure is a published gas-equivalent heating requirement for an unlit reference tomato greenhouse, not an observed gas meter reading from the planned greenhouse. The model prices the case in which that heating requirement is supplied entirely by gas. The Dutch case has no PV under the project’s site-space constraint.

03 / FULL PRODUCTION COST

Every annual cost item — nothing hidden

The 28 cost lines below are shown individually, including the original workbook notes. Figures are annual euro amounts for one hectare.

Annual cost item / 1 haNetherlands (€)Agadir (€)Explanation and basis
Labour and management
Greenhouse growing and harvesting labour€229.125,00€16.875,007.500 growing and harvesting hours; management budgeted separately
Greenhouse manager and crop management€30.000,00€14.000,00Annual budget estimate; not verified
Subtotal — Labour and management€259.125,00€30.875,00
Energy and grid
Natural gas, energy tax and CO₂ levy€227.153,44€0,00Netherlands: WUR reference heat demand of 209.000 m³ gas equivalent (not measured gas consumption); two 2026 energy-tax brackets plus CO₂ levy.
Grid electricity after direct use of PV power€40.350,00€66,36Annual load profile and supply contract unavailable; solar electricity is not free
Fixed electricity and grid charges€0,00€259,74Depends on contracted power and connection capacity
Subtotal — Energy and grid€267.503,44€326,10
Water and cultivation inputs
Water and water treatment€9.000,00€9.000,00Agadir water source not yet selected; provisional budget
Young plants and propagation material€18.000,00€18.000,00Same provisional budget pending local quotations
Nutrients and fertilisers€16.000,00€16.000,00Same provisional budget
Crop protection and pollination€14.000,00€14.000,00Biological crop protection and pollination, without double counting
Substrate, twine and clips€10.000,00€10.000,00Consumable supplies
Irrigation consumables and filters€7.000,00€7.000,00Fixed equipment is not charged twice
Supplementary CO₂ for crop enrichment€3.000,00€3.000,00Requirement and CO₂ source not yet determined
Subtotal — Water and cultivation inputs€77.000,00€77.000,00
Packing, quality and local transport
Packaging materials€20.000,00€20.000,00Cost per saleable kg; excludes greenhouse harvest and sorting labour
Outsourced sorting and pre-cooling€16.000,00€16.000,00Only additional outsourced costs; greenhouse labour is separate
Certification, residue and laboratory tests€6.000,00€6.000,00Traceability and laboratory testing
Domestic transport to regional export hub€15.000,00€15.000,00Does not include international freight to EU customers
Subtotal — Packing, quality and local transport€57.000,00€57.000,00
Land and business overhead
Land lease or annual land charge€20.000,00€8.000,00Do not also depreciate purchased land
Administration, banking and compliance€12.000,00€8.000,00Makes overhead costs visible
Sales and trading, fixed budget€10.000,00€10.000,00Transaction-based commissions not yet established
Waste disposal, cleaning and consumables€5.000,00€5.000,00Capital equipment maintenance accounted for separately
Subtotal — Land and business overhead€47.000,00€31.000,00
Annualised capital, finance and insurance
Greenhouse depreciation€75.000,00€75.000,0020-year useful-life assumption
Solar-thermal storage depreciation€0,00€20.000,00Annual depreciation calculated from the location-specific investment
Climate and irrigation equipment depreciation€20.000,00€20.000,00Same provisional investment
Solar PV depreciation€0,00€182,65PV equipment is not treated as cost-free
Sorting and cooling equipment depreciation€10.000,00€10.000,00No additional note in model
Interest on initial financing€54.000,00€63.082,19Year 1; principal repayments and equity return excluded
Equipment maintenance€36.000,00€42.054,79No double counting of growing consumables
Insurance premiums€18.000,00€21.027,40Quotation required for the actual insurance coverage
Subtotal — Annualised capital, finance and insurance€213.000,00€251.347,03
TOTAL / HECTARE / YEAR€920.628,44€447.548,14All 28 rows, including investment charges
PRODUCTION COST PER TONNE (400 t/ha)€2.301,57€1.118,87Annual total ÷ assumed saleable tonnes

Labour

7.500 hours × €30,55/hour (Netherlands) or €2,25/hour (Agadir scenario), plus separate supervision. The Agadir hourly amount is not a verified sector wage.

Annualised investments

Greenhouse, crop automation, thermal storage, PV and packing equipment are charged through depreciation, interest, maintenance and insurance. Their purchase values are not expensed in full again.

Equal shared services

Identical budgets for growing supplies, packing and sorting are retained in the absolute totals; they cancel in the difference only if actual services and quantities prove equal.

04 / ENERGY COSTS

How the gas and electricity amounts are calculated

Power consumption, imported grid electricity and PV electricity are different quantities. The local equipment ratings still need supplier confirmation.

Netherlands: purchased energy

ComponentCalculationAnnual cost
Gas purchased209.000 m³ × €0,89/m³€186.010,00
Gas energy tax, first band170.000 m³ × €0,18020€30.634,00
Gas energy tax, second band39.000 m³ × €0,15881€6.193,59
Gas CO₂ charge209.000 m³ × €0,02065€4.315,85
Gas and applicable chargesSum of four lines€227.153,44
Purchased electricity150.000 kWh × €0,269/kWh€40.350,00
NET PURCHASED ENERGYGas + electricity€267.503,44

Dutch electricity is the H1 2026 CBS price for the modelled business-consumption band. Gas €0,89/m³ is a market snapshot from 15 November 2026, not a long-term supply contract. The 209.000 m³ figure represents the full reference heat requirement modelled as gas consumption.

Agadir: estimated electrical devices for one hectare

Greenhouse installationCalculation basis (preliminary)kWh/year
Irrigation pumps10.000 m³; 35 m head; 60% efficiency1.589
Water-recycling pumps2.000 m³; 15 m head; 55% efficiency149
Fertiliser dosing1 kW × 1 h × 300 days300
Filtration and UV0,5 kW × 3 h × 300 days450
Climate computer and sensors0,15 kW × 8.760 h1.314
Automatic vents10 × 0,37 kW × 0,25 h × 300 days278
Shade screen motors8 × 0,37 kW × 1/6 h × 300 days148
Heating, grow lighting, mechanical dehumidificationNot fitted in Agadir base case0
TOTAL EQUIPMENT ELECTRICITYPreliminary design calculation4.228 kWh

The individual consumption figures above are assumptions from an initial sizing exercise. No manufacturer schedule, irrigation head curve or real operating-hours log has yet been provided. Water desalination, common sorting, packing, cold storage and any additional cooling are not included in this core equipment-only estimate; those may differ by location and must be evaluated before a complete footprint is claimed.

Agadir: net electricity after on-site solar PV

ComponentCalculationAnnual result
Total electricity for listed greenhouse equipmentSum of the seven device categories4.228 kWh
PV electricity used directlyIllustrative overlap of sunshine and equipment use3.571 kWh
Residual grid import4.228 − 3.571657 kWh
Purchased grid electricity657 kWh × €0,10100457/kWh€66,36
Grid capacity chargeIllustrative agricultural connection€259,74
Grid purchases and capacitySum of above cost components€326,10

Do not interpret 657 kWh as a forecast. The 3 kWp PV capacity and 3.571 kWh self-use are model inputs, not a verified hour-by-hour solar production simulation. PV depreciation, loan interest, maintenance and insurance appear in the full cost table. The solar-thermal reserve is not an electrical-heating requirement.

05 / CO₂ FROM PRODUCTION

Energy-related CO₂ emissions while growing tomatoes

Calculated from the model's gas use, purchased net electricity and life-cycle PV electricity. The numbers below are not a complete product carbon footprint.

Netherlands · production energy482,61 t CO₂e1.206,52 kg CO₂e per tonne of tomatoes
Agadir · production energy0,62 t CO₂e1,54 kg CO₂e per tonne of tomatoes
Emissions calculation / year / hectareNetherlandsAgadir
Natural gas use209.000 m³ × 2,134 kg CO₂e/m³0 m³
Natural gas CO₂e446,006 tonnes0 tonnes
Purchased grid electricity150.000 kWh × 0,244 kg CO₂e/kWh657 kWh × 0,602 kg CO₂e/kWh
Grid electricity CO₂e36,600 tonnes0,396 tonnes
On-site PV, life-cycle estimateNone3.571 kWh × 0,062 kg CO₂e/kWh
PV-related CO₂e0 tonnes0,221 tonnes
TOTAL ENERGY-RELATED CO₂e482,606 tonnes/year0,617 tonnes/year
PER TONNE SALEABLE TOMATOES (400 t/ha)1.206,52 kg CO₂e/t1,54 kg CO₂e/t
PER KILOGRAM SALEABLE TOMATOES1,2065 kg CO₂e/kg0,0015 kg CO₂e/kg
Transparency warning: The very large modelled energy-only difference arises mainly because the Dutch case assumes the full published heat demand is supplied by natural gas, while the Agadir case assumes no heating and a very small unverified equipment electrical load. It must not be advertised as a measured reduction in the total CO₂ footprint. The electricity factors come from different inventories and have not been harmonised to a certified LCA boundary.

Production emissions still to be measured or modelled

Greenhouse and energy hardware

Steel, glazing, plastics, irrigation machinery, PV manufacture and thermal storage, allocated by real lifetime.

Fertilisers and inputs

Manufacture and transport of plant material, nutrient solution, substrate, crop-protection products and associated direct emissions.

Water and waste

Supply, treatment, recycling, crop residues, refrigerant leakage and any supplementary CO₂ enrichment.

06 / SENSITIVITY

What happens if production differs?

Price per tonne changes with actual saleable yield. The initial model varies packaging and outsourced sorting (€90/t together) in line with output, while all other annual amounts stay unchanged.

Annual saleable yieldNetherlands / tAgadir / tDifference / t
200 t/ha/year€4.513,14€2.147,74€2.365,40
250 t/ha/year€3.628,51€1.736,19€1.892,32
300 t/ha/year€3.038,76€1.461,83€1.576,93
350 t/ha/year€2.617,51€1.265,85€1.351,66
400 t/ha/year€2.301,57€1.118,87€1.182,70
450 t/ha/year€2.055,84€1.004,55€1.051,29
500 t/ha/year€1.859,26€913,10€946,16
550 t/ha/year€1.698,42€838,27€860,15
600 t/ha/year€1.564,38€775,91€788,47

This is a mathematical sensitivity table rather than a prediction. Real labour, fertiliser, energy and post-harvest expenses will also move with output.

Netherlands: varying actual gas consumption

Purchased gasTotal annual costs NLCost per tonne
0 m³€693.475,00€1.733,69
25.000 m³€720.746,25€1.801,87
50.000 m³€748.017,50€1.870,04
75.000 m³€775.288,75€1.938,22
100.000 m³€802.560,00€2.006,40
150.000 m³€857.102,50€2.142,76
209.000 m³€920.628,44€2.301,57

Other inputs remain constant. If a Dutch site has a non-fossil heat source, its actual installation costs and emissions must replace the modelled natural gas system. A lower gas number without accounting for replacement heat is not a full alternative scenario.

07 / SALES & DELIVERY

Two production locations, one European trade network

Commercial orders can be managed through Dutch and European partners while actual shipments go directly to the buyer from the better-positioned greenhouse.

Netherlands → European buyer

Sell via the shared network, deliver directly from the Dutch production site.

Agadir → European buyer

Sell through the same network, deliver directly to Spain, France, Italy or other markets without routing via Rotterdam.

Optimised logistics

Compare total transport costs, route emissions, shelf-life, quality and delivered price for each actual contract.

Not priced: International reefer freight, shipping, customs and product-specific border costs are unfilled in the Excel model. The €2.301,57 and €1.118,87 figures are regional export-hub production costs, not delivered prices in Italy, France or elsewhere.

The proposed 450-hectare development

At the hypothetical model output of 400 t/ha, 450 hectares of actual production greenhouses would produce 180.000 tonnes/year. A 450-hectare gross site includes roads, infrastructure, water storage and services, so its net greenhouse area could be smaller. This is a scale illustration, not a production forecast.

08 / SOURCES & MODEL

Independent verification is possible

Source links and the exact 15 November Excel calculation are available for review. Measurements, supplier quotes and the full product life-cycle inventory are the next steps.

  1. Dutch government study citing WUR unlit tomato greenhouse energy reference — 20,9 m³ gas-equivalent heat and 15 kWh electricity per m².
  2. Statistics Netherlands (CBS) — indicative H1 2026 business electricity cost for the specified consumption band.
  3. Dutch Tax Administration — 2026 greenhouse-gas energy-tax brackets.
  4. 2026 greenhouse labour-cost example — Dutch €30,55/productive hour, job and method dependent.
  5. ONEE Morocco — agricultural electricity prices and capacity charges, contingent on contract.
  6. Dutch natural gas emissions factor — model uses 2,134 kg CO₂e/m³.
  7. Dutch grid / PV life-cycle emissions factors — model uses 0,244 and 0,062 kg CO₂e/kWh.
  8. Moroccan grid-emissions estimate, 2025 — model uses 0,602 kg CO₂e/kWh.
  9. Wageningen KWIN Greenhouse Horticulture 2026 — reference for detailed crop-specific operational budgets.
Research status: Supplier offers, employment quotations, detailed climate/heat modelling, measured irrigation energy, hourly PV self-consumption, real saleable yields and precise water and transport arrangements remain to be confirmed. Do not present the extreme energy-only CO₂ result as the complete climate impact of a tonne of tomatoes.

Download full calculation workbook ↓

Invest in a verifiable horticulture model.

Growers, technology companies and investors can discuss the commercial potential and independent verification of the Westland Agadir Centre model.

Contact Westland Agadir Centre ↗