How do I check the construction progress of an apartment in Agadir?
The answer depends on whether you are the buyer of an off-plan apartment or the owner of a property under construction. For an off-plan buyer, the construction progress is checked against the payment schedule: each payment is triggered by a milestone, and the buyer has the right to verify that the milestone has been reached before releasing the funds. For an owner building on their own plot, the progress is checked through independent site visits and the payment applications that the contractor submits. In both cases, the principle is the same: the money follows the work, not the other way around.
This article explains how to check the construction progress of an apartment in Agadir, what evidence to request, and how to protect yourself if the progress does not match the plan.
The VEFA buyer: progress tied to payment milestones
If you have purchased an off-plan apartment under the VEFA framework (Law 44-00), the construction progress is not a matter of trusting the developer's updates. The law ties each payment to a specific stage of the construction, and the buyer is entitled to evidence before releasing the funds.
The legal schedule is: 20% at the preliminary contract, 30% at the structural works, 30% at the watertight and airtight stage, and 20% at delivery. At each milestone, the developer should provide the evidence that the stage has been reached: the architect's certificate for the structural works, confirmation that the roof and exterior joinery are installed for the watertight stage, and a contradictory acceptance report for the delivery .
The practical implication is that the buyer should not pay on a calendar date alone. The payment should be triggered by the evidence that the work has been done. A developer who asks for a payment without the supporting evidence is a developer who is asking the buyer to take on a risk that the law does not require.
The independent inspection: your eyes on the site
For a buyer who lives abroad, the developer's certificates are not enough. The buyer needs an independent professional to visit the site and confirm that the construction matches the milestone.
ReaConsult's guidance for remote owners is direct: the owner who is present walks their site, observes, asks questions, and rejects a defect before it is covered up. The remote owner cannot do this unless the eye is delegated to an independent technical third party. The stage-by-stage inspection visits are the keystone of the remote system, and the reports should include dated photographs and a clear status .
Soustraitant.ma describes the process in similar terms: an engineer visits the site at each critical stage, checks the technical points (diameters, spacing, dosages, thicknesses), documents the visit with photographs, and assesses whether the stage is compliant to continue. The report is sent directly to the owner, not through the contractor, so that the owner can decide whether to release the next payment .
The practical implication is that the independent inspection is not a luxury. It is the mechanism that allows the remote buyer to verify the progress before paying. A developer who resists an independent inspection is a developer who has something to hide.
The administrative check: permits and authorisations
The construction progress is not only about the physical work. It is also about the administrative status of the project. The Agadir commune provides an online service to track the status of a building or housing permit application, using the file number . That service allows the buyer to verify that the permit is in order and that the project is authorised.
The buyer should also verify that the project has the required authorisations to sell off-plan. The 2015 reform of the VEFA framework (Law 107-12) introduced the completion guarantee and the reservation contract, and it requires the seller to provide the bank guarantee or the equivalent security before the notary releases the funds .
The practical implication is that the administrative check is part of the progress check. A project that is physically advanced but administratively irregular is not a project that the buyer should continue to fund.
The owner building on their own plot: payment applications and site visits
If you are building an apartment on your own plot in Agadir, rather than buying off-plan, the progress check follows a different logic. The contractor submits payment applications (situations de paiement) that break the work into milestones, and each release of funds is conditional on the validation of the previous stage.
ReaConsult's checklist for remote construction is explicit: the written works contract should set out the scope, the price, the deadlines, the materials and the acceptance conditions. The payment schedule should be tied to the progress, not to the calendar. And the owner should provide for a retention until the reserves are lifted, to keep financial leverage to the very end .
The practical implication is that the owner who builds on their own plot needs the same discipline as the off-plan buyer: a written contract, a payment schedule tied to progress, and an independent inspection before each payment.
The Agadir context
Agadir has an active off-plan market, with several developers launching projects in different districts. The VEFA framework applies to all of them, and the progress check is the mechanism that protects the buyer. But the quality of the developers varies, and the buyer should not assume that the certificates and the reports are accurate without independent verification.
The city is also expanding, with municipal planning for Temsia providing for a development area of around 62 km² with capacity for a future population of 76,585 by 2035. New residential districts are extending the city's footprint, and the construction activity is concentrated in these areas.
So how do you check?
For the VEFA buyer: check the milestone against the legal schedule, request the supporting evidence, and commission an independent inspection before releasing each payment. For the owner building on their own plot: use a written contract, tie the payments to the progress, and commission the same independent inspections.
The buyers who do well are the ones who treat the progress check as a condition of payment, not as a courtesy. The ones who struggle are the ones who pay on the developer's word, and discover at the handover that the construction has not reached the stage they paid for.
Investment opportunities with Agadir Investment
Agadir Investment works with international buyers seeking exposure to the Agadir property market and the wider Souss region. There are two principal routes.
1. Property investment
Investors can purchase property in Agadir across a range of types: apartments, new-build residences, villas, holiday homes, buy-to-let properties and long-term holdings. Agadir Investment also provides property management services, so owners who do not live in Morocco can have their property managed on their behalf — covering day-to-day operations, guest or tenant handling, and maintenance coordination — without needing to be present.
2. Investment in property development
For larger investors, there is the option to invest directly in the financing and development of property projects. For investments from €5,000,000, Agadir Investment states a fixed, guaranteed return of 7% per year. This is not an estimated or variable return but the stated fixed rate, subject to the applicable contractual terms. Investors considering this route should review those terms carefully with their own advisers before committing.
Contact
To discuss either route, or to request current availability and documentation, contact Agadir Investment at agadirinvestment.com or by email at info@agadirinvestment.com.